Give-A-Day Projects
Dorm Extension
We are in the middle of adding much needed gender-specific study areas, laundry rooms, and student lounge areas to the dorm. Jeremy Troyer is working to complete the dorm extension by first term 2019 as funds are available. Continued donations are still needed to finish this project. We are grateful for your generous financial support and volunteer labor. To give toward the dorm extension click on the donate button below.
We have over 200 light fixtures in the main building and dorms that use a significant amount of energy. With rebates from the power company and the savings we would experience by upgrading to LED bulbs, we would largely offset the cost of the purchase of new bulbs within the first year.
EBI has enjoyed the use of the Long Street house for the past 10 years. However, several issues have made it difficult to fully utilize the house because of the current layout. Plans are to divide the house into three apartments which will greatly increase the usability of the space available. At this time, we intend to complete only the upstairs entrance. We hope to do additional renovations over the next few years.
Funding Progress
Donate Donate Donate Donate Donate Donate
Amount Given
Total Needed
100%
$3,035
100%
100%
School Building & Dorms
402 Dorm Building
Funding Progress - Phase 1
Total Given
Total Needed
$41,700
$41,700
Funding Progress
100%
Amount Given
Total Needed
100%
$3,000
100%
100%
Upstairs Exterior Entrance
402 Dorm Building
LED Bulbs (Energy Saving)
100%
100%
Exterior Dorm Extension
402 Dorm Building
$3,000
$3,035
Construction Progress
100%
100%
Exterior Entrance
402 Dorm Building
Construction Progress
100%
100%
100%
Total
402 Dorm Building
Construction Progress - Phase 1
100%
100%
Progress
402 Dorm Building
100%
100%
School Building & Dorms
402 Dorm Building
© Elnora Bible Institute, 2019
The hood over the range in the kitchen exhausts air through the roof of the kitchen. To replace the air that is exhausted, outside air needs to come in through cracks around windows and doors. The outside air is not heated or cooled. This situation can cause mold above the ceilings and at some walls and increases the heating/cooling costs. To correct this problem a new outdoor air fan would be installed on the roof over the kitchen and deliver heated make-up air right at the hood.
Donate Donate
Funding Progress
$4,800
$4,800
Amount Given
Total Needed
$900
$900
$6,900
100%
100%
100%
100%
201 Equipment
202 Roofing
203 Electric & Gas
Total
100%
100%
Total
402 Dorm Building
$1,200
$1200
$6,900
Funding Progress - Phase 2
$44,900
$44,900
Total Given
Total Needed
$18,600
$18,600
$32,700
$28,800
100%
100%
100%
100%
100%
110 Mechanical
111 Drywall
112 Trim/Flooring
113 Furniture
105 Windows
$32,700
$125,000
$28,800
$125,000
100%
100%
Total
402 Dorm Building
Make-up Air System for the Kitchen Exhaust (Energy Saving) Main Priority Priority  Level 1
Construction Progress - Phase 2
85%
100%
Progress
402 Dorm Building
During the recent installation of a required firewall in the middle hallway, we discovered mold behind the existing drywall. With minimal costs, we were were able to replace the mold-covered drywall. However, there are also windows in the front hallway that are not well insulated and need to be replaced. Because of this, we would anticipate renovating the south and front hallways while completing our work in the middle hallway.    Donate Funding Progress		 Total Given Total Needed   Construction Progress		 Hallway Updates  $22,950  $22,950 Donate Long Street House
Give-A-Day Projects
Dorm Extension
We are in the middle of adding much needed gender-specific study areas, laundry rooms, and student lounge areas to the dorm. Jeremy Troyer is working to complete the dorm extension by first term 2019 as funds are available. Continued donations are still needed to finish this project. We are grateful for your generous financial support and volunteer labor. To give toward the dorm extension click on the donate button below.
We have over 200 light fixtures in the main building and dorms that use a significant amount of energy. With rebates from the power company and the savings we would experience by upgrading to LED bulbs, we would largely offset the cost of the purchase of new bulbs within the first year.
Funding Progress
Donate Donate Donate Donate
School Building & Dorms
402 Dorm Building
Funding Progress - Phase 1
Funding Progress
Upstairs Exterior Entrance
402 Dorm Building
LED Bulbs (Energy Saving)
Exterior Dorm Extension
402 Dorm Building
Construction Progress
Exterior Entrance
402 Dorm Building
Construction Progress
Total
402 Dorm Building
Construction Progress - Phase 1
Progress
402 Dorm Building
School Building & Dorms
402 Dorm Building
© Elnora Bible Institute, 2019
Funding Progress
201 Equipment
202 Roofing
203 Electric & Gas
Total
Total
402 Dorm Building
Funding Progress - Phase 2
110 Mechanical
111 Drywall
112 Trim/Flooring
113 Furniture
105 Windows
Total
402 Dorm Building
Make-up Air System for the Kitchen Exhaust (Energy Saving)
Construction Progress - Phase 2
Progress
402 Dorm Building
During the recent installation of a required firewall in the middle hallway, we discovered mold behind the existing drywall. With minimal costs, we were were able to replace the mold-covered drywall. However, there are also windows in the front hallway that are not well insulated and need to be replaced. Because of this, we would anticipate renovating the south and front hallways while completing our work in the middle hallway.    Donate Funding Progress		 Total Given Total Needed   Construction Progress		 Hallway Updates  $22,950  $22,950 Donate
Long Street House