Front Hallway
© Elnora Bible Institute, 2017
Elnora Bible Institute  Equipping DISCIPLES to Show the WAY
Give-A-Day Projects
We   have   completed   the   interior   front   entrance   remodel,   the   new   chapel,   and   the   Indian Street   house   is   paid   off.      However,   there   are   a   few   other   projects   we   are   still   working   on, predominantly   the   dorm   extension.   Our   goal   is   to   begin   the   dorm   extension   this   coming spring   with   the   funds   God   provides   through   the   Give-A-Day   effort.   In   the   meantime,   we have   begun   phase   one   of   remodeling   the   Long   Street   house   into   three   separate   apartments to   provide   necessary   housing   for   families   who   come   to   teach   and/or   take   classes   at   EBI. Also,    in    order    to    save    on    energy    costs,    we    want    to    convert    all    our    lights    in    the    main buildings to LED and replace the windows in the Institute’s front hall.
Dorm Extension
We   hope   to   add   a   much   needed   gender-specific study    area,    laundry    room,    and    student    lounge. Currently,   there   is   no   area   in   the   school   that   is appropriately   set   up   to   study.   The   concrete   has been    poured    and    is    ready    for    a    building.    Our immediate   goal   is   to   raise   the   money   needed   to dry-in   the   dorm   extension.   Continued   donations will   be   needed   beyond   phase   one   to   complete this    project.        Having    the    building    dried-in    will enable   us   to   work   on   this   project   as   funds   are available.
The     hood     over     the     range     in     the     kitchen exhausts   air   through   the   roof   of   the   kitchen.      To replace    the    air    that    is    exhausted,    outside    air needs     to     come     in     through     cracks     around windows    and    doors.        The    outside    air    is    not heated    or    cooled.        This    situation    can    cause mold   above   the   ceilings   and   at   some   walls   and increases   the   heating/cooling   costs.      To   correct this   problem   a   new   outdoor   air   fan   would   be installed    on    the    roof    over    the    kitchen    and deliver heated make-up air right at the hood. 
We   have   over   200   light   fixtures   in   the   main   building   and   dorms that   use   a   significant   amount   of   energy.   With   rebates   from   the power    company    and    the    savings    we    would    experience    by upgrading   to   LED   bulbs,   we   would   largely   offset   the   cost   of   the purchase of new bulbs within the first year. 
During    the    recent    installation    of    a    required    firewall    in    the    middle hallway,   we   discovered   mold   behind   the   existing   drywall.   With   minimal costs,    we    were    were    able    to    replace    the    mold-covered    drywall. However,   there   are   also   windows   in   the   front   hallway   that   are   not   well insulated    and    need    to    be    replaced.    Because    of    this,    we    would anticipate   renovating   the   south   and   front   hallways   while   completing our work in the middle hallway.
EBI    has    enjoyed    the    use    of    the    Long    Street house   for   the   past   10   years.   However,   several issues   have   made   it   difficult   to   fully   utilize   the house   because   of   the   current   layout.   Plans   are to    divide    the    house    into    three    apartments which   will   greatly   increase   the   usability   of   the space    available.    At    this    time,    we    intend    to complete   only   the   upstairs   entrance.   We   hope to   do   additional   renovations   over   the   next   few years.
Main Priority Priority  Level 1 Priority  Level 2
Funding Progress
Priority  Level 3 Donate Donate Donate Donate Donate Donate Donate Donate Donate Donate
$2,521
100%
100%
$0
Amount Given
Total Needed
100%
$514
$0
$3,035
$0
0%
0%
100%
401 School Building
402 Dorm Building
Total
0%
100%
Total
402 Dorm Building
100%
Funding Progress
$10,000
100%
100%
$325
Total Given
Total Needed
100%
$7,000
$0
3%
0%
0%
0%
0%
0%
0%
0%
100%
101 Exterior Walls
102 Tresses
103 Roof Sheeting
104 Shingles
105 Windows
106 Doors
107 Siding
108 Brick
Total
100%
100%
100%
100%
100%
$325
$41,700
$4,500
$0
$4,000
$0
$3,000
$0
$5,000
$0
$3,200
$0
$5,000
$0
Funding Progress
$3,000
100%
100%
$0
Amount Given
Total Needed
100%
$3,000
$0
0%
100%
301 Upstairs Exterior Entrance
402 Dorm Building
100%
0%
100%
Total
402 Dorm Building
LED Bulbs (Energy Saving) Make-up Air System for the Kitchen Exhaust (Energy Saving)
Funding Progress
$4,800
100%
100%
$0
Amount Given
Total Needed
100%
$900
$0
$6,900
$0
0%
0%
0%
100%
201 Equipment
402 Roofing
203 Electric & Gas
Total
0%
100%
Total
402 Dorm Building
100%
$1,200
$0
Hallway Updates
Funding Progress
$1,160
100%
100%
$0
Total Given
Total Needed
100%
$800
$0
0%
0%
0%
0%
0%
0%
0%
0%
0%
100%
501 Refinishing Walls
502 Electrical
503 Flooring
504 Base
505 Ceiling Grid
506 Lights
507 Paint
508 New Windows
509 Fireplace
Total
100%
100%
100%
100%
100%
$575
$0
$2,025
$0
$550
$0
$400
$0
$150
$0
$300
$0
100%
$0  $15,060 100%
0%
100%
Total
402 Dorm Building
$9,000
$0
Middle Hallway
$1,755
100%
100%
$0
Total Given
Total Needed
100%
$585
$0
0%
0%
100%
510 Flooring
511 Base
103 Roof Sheeting
$0  $2,340 100%
0%
100%
Total
402 Dorm Building
South Hallway
$750
100%
$0
Total Given
Total Needed
100%
$3,400
$0
100%
100%
100%
$500
$0
$1,000
$0
$700
$0
$300
$0
0%
0%
0%
0%
0%
0%
100%
512 Refinishing Walls
513 Flooring
514 Base
515 Drinking Fountain
516 Water Bottle Station
517 Paint
107 Siding
100%
$0
$6,650
100%
0%
100%
Total
402 Dorm Building
Priority  Level 4 100%
1%
100%
Total
402 Dorm Building
Long Street House